Chennai Metro Purple Line OMR: Latest Construction Updates

100% piling complete. December 2026 operational debut.

Learn More

Chennai Metro's Purple Line OMR Stretch Achieves Major Milestone—But Timeline Shifts

Chennai Metro Rail Limited has completed 100% of piling works—totaling 3,066 piles—between Nehru Nagar and Sholinganallur along Old Mahabalipuram Road (OMR) on Corridor 3. The project also achieved a perfect record in structural casting, completing all 582 precast prestressed U-Girders. This marks a decisive step forward in the Phase 2 expansion, yet the operational timeline has shifted from initial targets.

The 20-kilometer elevated line on OMR from Nehru Nagar to Siruseri Sipcot, originally slated to open by June 2026, is now expected to commence operations by December 2026. Revisions to the designs for the grade separators and the metro line at the Sholinganallur and Thoraipakkam junctions have resulted in a potential six-month delay, pushing the estimated completion date from June 2026 to December 2026. Despite this pushback, the Thoraipakkam and Sholinganallur junction required traffic navigating which was critical, with the requirement to integrate two metro stations through flyovers while managing uninterrupted traffic flow.

Chennai Metro Corridor 3, also known as Purple Line, has been planned under Phase 2 and is currently under construction. The corridor is a 45.8km stretch from Madhavaram to SIPCOT. It passes through Thiruvanmiyur, Perungudi, Thoraipakkam, Sholinganallur, Navalur, and Siruseri.

For property buyers and investors, the implications are significant. Current portal data places Perungudi at ₹10,980-11,250 per sq ft, Sholinganallur at around ₹8150 per sq ft, and Navalur within a broad ₹6000-8500 band. Perambur, sitting directly on the Purple Line corridor, posted a 35% year-on-year jump, the strongest in the city, which the report attributes to infrastructure upgrades and metro connectivity.

The Sholinganallur station, in particular, will serve as a critical interchange hub. Sholinganallur metro station is slated to be operational by March 2027, making it a key metro rail hub of South Chennai. The Chennai Metro Rail Limited is constructing an interchange station between corridors 3 and 5 at Sholinganallur, where as per the multi-layered structure, corridor 3 will be the lower level and corridor 5 will be on top.

The expanded Purple Line network promises to reshape commuter patterns across Chennai's IT corridor. Corridor 3 & Corridor 5 Phase 2 lines will eliminate peak hour traffic congestion along Old Mahabalipuram Road (OMR). With structural work now firmly in place and the final operational push set for late 2026, the era of metro-connected OMR real estate is drawing near.

PURAVANKARA Projects

PURAVANKARA SOUTH-EAST BENGALURU (ELECTRONIC CITY CORRIDOR)
Acquisition

PURAVANKARA SOUTH-EAST BENGALURU (ELECTRONIC CITY CORRIDOR)

Electronic City Corridor, Bangalore

Configuration to be announced • Price on Request

7.83-acre residential development, ₹1,100 Cr GDV

PURAVANKARA BHANDUP
Upcoming

PURAVANKARA BHANDUP

Bhandup, Mumbai

2, 3, 4 BHK • Price on request

Joint development on LBS Marg, Bhandup West

Puravankara Codename Arbor
Upcoming

Puravankara Codename Arbor

Gunjur, Varthur, Bangalore

2, 3 BHK • On Request

Upcoming homes on the Whitefield-Sarjapur belt

Puravankara Doddagubbi Bengaluru
Upcoming

Puravankara Doddagubbi Bengaluru

Doddagubbi, North Bengaluru

2, 3 BHK (proposed) • Price on request

11.23-acre JDA, ₹1,100 Cr GDV

Puravankara Dombivli
Upcoming

Puravankara Dombivli

Sonar Pada, Dombivli East, Mumbai

2, 3, 4 BHK • Price on Request

Upcoming homes off Kalyan-Shilphata Road

Puravankara Hennur Road Bengaluru
Upcoming

Puravankara Hennur Road Bengaluru

Hennur Road, Bengaluru

2, 3 BHK (expected) • Price on request

₹1,300 Cr GDV, 0.84 mn sq ft

Puravankara Mandur Budigere Bengaluru
Upcoming

Puravankara Mandur Budigere Bengaluru

Mandur, Budigere, Bangalore

2, 3 BHK (expected) • Price on request

14.57-acre residential development, GDV ₹2,300 Cr

Puravankara Marine Drive 2
Upcoming

Puravankara Marine Drive 2

Marine Drive, Kochi

1, 2, 3 BHK • Price on Request

Upcoming waterfront address near Marine Drive

Enquire

Get in Touch

Back

Reference & FAQ

When will the OMR metro section be fully operational?
The 20-kilometer elevated line on OMR from Nehru Nagar to Siruseri Sipcot is now expected to commence operations by December 2026, with the Sholinganallur metro station slated to be operational by March 2027.
What caused the delay from June 2026 to December 2026?
Revisions to the designs for the grade separators and the metro line at the Sholinganallur and Thoraipakkam junctions resulted in a six-month delay. The redesign was necessary to integrate two metro stations safely through flyovers while managing live traffic.
What major construction milestones have been achieved?
CMRL completed 100% of piling works—totaling 3,066 piles—between Nehru Nagar and Sholinganallur on Corridor 3, and completed all 582 precast prestressed U-Girders.
Which stations will be along the OMR stretch?
The corridor passes through Thiruvanmiyur, Perungudi, Thoraipakkam, Sholinganallur, Navalur, and Siruseri. Sholinganallur metro station is a key metro rail hub slated for March 2027 operational status.
What is the Sholinganallur interchange station?
CMRL is constructing an interchange station between corridors 3 and 5 at Sholinganallur, where corridor 3 will be the lower level and corridor 5 will be on top. This enables seamless transfer between two Phase 2 corridors.
How much has property appreciated near Purple Line areas?
Perambur, sitting directly on the Purple Line corridor, posted a 35% year-on-year jump, the strongest appreciation in the city.
What are current property rates along OMR?
Current portal data places Perungudi at ₹10,980-11,250 per sq ft, Sholinganallur at around ₹8150 per sq ft, and Navalur within a broad ₹6000-8500 band.
Will the OMR metro reduce traffic congestion?
Corridor 3 & Corridor 5 Phase 2 lines will eliminate peak hour traffic congestion along Old Mahabalipuram Road.
How long is the Purple Line OMR stretch?
Corridor 3 is a 45.8km stretch from Madhavaram to SIPCOT, with the 20-kilometer elevated section on OMR from Nehru Nagar to Siruseri Sipcot.
Who executed the piling and structural work?
The project team, working under contract package C3/EV-01 executed by Larsen & Toubro, completed all 3,066 piles and 582 precast prestressed U-girders along the busy corridor.

Presented for informational reference only; not an offer or a contract. All particulars — pricing, dimensions, imagery — are subject to change without notice. Independent verification is recommended before deciding. About · Projects